CIMC Raffles starts construction of Shandong Energy booster station

3 min read
CIMC Raffles starts construction of Shandong Energy booster station

On March 10, the construction of the offshore booster station project of Shandong Energy Group Bozhong Offshore Wind Power Site A project undertaken by CIMC Raffles started in Haiyang Base. The Bozhong Offshore Wind Power Site A project of Shandong Energy Group is the first affordable offshore wind power project in Shandong Province, and also the first approved project after offshore wind power entered the era of parity, marking the official entry into the era of affordable development of offshore wind power. The capacity of the 220KV offshore booster station started this time is 500MW, which is the largest single-scale offshore booster station in the northern region, and the first officially built offshore booster station in the era of offshore wind parity in Shandong Province.

The construction of the offshore booster station is one of the most important main lines of the offshore wind farm, which directly restricts the grid connection progress of the project; the construction of the offshore booster station of this project has officially started, which is a solid step to ensure full-capacity grid connection by the end of the year. With the joint efforts of all parties involved in the construction, the Shandong Energy Group Bozhong Offshore Wind Power Site A project is anchoring the goal of the first grid-connected affordable offshore wind power project at full speed and steadily.

This project opened the curtain of cooperation between CIMC Raffles and Shandong Energy Group New Energy Company and China Power Construction Group Zhongnan Survey and Design Research Institute Co., Ltd. Among them, CIMC Raffles, as a leading provider of offshore engineering equipment in China, has been deployed in the offshore wind power field for several years and has developed different types of wind power equipment such as self-installation booster stations, modular booster stations, and 3060 series wind power installation vessels. , delivered a batch of advanced, high-quality wind power projects. Shandong Energy Group New Energy Company, as a provincial-level new energy investment platform in Shandong Province, is making every effort to promote the development of the Bozhong Offshore Wind Power Base project at full speed. The general contractor, Zhongnan Survey and Design Research Institute Co., Ltd., has strong strength and excellent technology and has built many iconic projects at home and abroad. All parties have the same strategic direction in the field of clean energy, and the industry is highly coordinated. In addition to offshore wind power, cooperation in other new energy fields will also be discussed.

At present, at a critical period in the restructuring of the global energy structure, countries are scrambling to deploy strategic layouts in the field of offshore wind power to seize development opportunities. Shandong Offshore Wind Power Base is one of the large clean energy bases planned and laid out in my country’s “14th Five-Year Plan”. With the orderly advancement and smooth commissioning of Bozhong Wind Farm, it will help Shandong build a “powerful offshore wind power province” and anchor my country Make a positive contribution to the grand goal of “3060”.

Source: eworldship

中集来福士承建山东能源集团渤中海上升压站开工

3月10日,中集来福士承建的山东能源集团渤中海上风电A场址工程海上升压站项目在海阳基地开工,该项目由中国电建集团中南勘测设计研究院有限公司总承包。

山东能源集团渤中海上风电A场址工程是山东省首个平价海上风电项目,也是海上风电进入平价时代后第一个取得核准的项目,标志着海上风电正式步入平价开发时代。本次开工建造的220KV海上升压站容量500MW,为北方地区单体规模最大的海上升压站,也是山东省海上风电平价时代第一个正式建造的海上升压站。

海上升压站建造是海上风电场最重要的主线之一,直接制约项目并网进度;本项目海上升压站正式开工建设,为确保年底全容量并网走出了坚实一步。在参建各方共同努力下,山东能源集团渤中海上风电A场址工程项目正锚定第一个并网的平价海上风电项目目标全速稳健推进。